Tuesday, January 18, 2011

Day 4

Tuesday 18th January 2011

Work really starts today! Contractor arrives on site.

They start by taking the roof tiles off the rear dormer, exposing the existing roof timbers, and allowing them to start constructing the new structure.

Building Inspector from the Building Control department of our local authority, Chorley Borough Council arrives to perform their initial inspection.

Also, the scaffold is erected at the front of the house.